Gorajec bypass over halfway complete: 6.6 km road to relieve three villages
🇵🇱 Poland

Gorajec bypass over halfway complete: 6.6 km road to relieve three villages

Construction of the Gorajec bypass on national road 74 between Janów Lubelski and Zamość has reached 55 percent completion. The new route will be 6.6 km long and will bypass the villages of Gorajec-Zastawie, Gorajec-Stara Wieś and Gorajec-Zagroble. Work on site includes engineering structures, pavement, slopes, culverts, lighting and a utility trench.