S17 construction from Tomaszów Lubelski to Hrebennego over halfway done
🇵🇱 Poland

S17 construction from Tomaszów Lubelski to Hrebennego over halfway done

Construction of the 17-kilometre expressway section S17 from Tomaszów Lubelski to Hrebennego has reached 53 per cent completion. Bituminous works, acoustic screen installation and viaduct concreting are underway. Budimex is carrying out the contract worth approximately 718.6 million zlotys under an agreement signed in November 2022. Permission for the road investment (ZRID) was issued on 28 May 2025.