Oracle's massive 1.3 GW data center campus in Port Washington, Wisconsin, known as Project Lighthouse, may not receive power before 2027. A regulatory commission invalidated a ten-month review and restarted it after grid operator ATC submitted 564 additional documents. Buildings are under construction but the campus cannot serve clients at full scale without approved transmission infrastructure.